The Quorn Park Hybrid Project consists of the construction and operation of a solar farm consisting of photovoltaic (PV) modules, a Battery Energy Storage System (BESS) and related civil and electrical infrastructure. The Project is located approximately ten kilometres northwest of Parkes.
The construction of the Quorn Park Hybrid Farm has an investment value of over $190 million. The estimated construction timeframe for the plant is expected to be approximately 18 months, while the farm’s operational life is approximately 35 years.
Pre-construction site studies and preconstruction works occurred in late 2024, and the construction phase of the project will commence in coming weeks.
The relevant Development Approvals for the Quorn Park Hybrid Project have been obtained from the Parkes Shire Council.
The planning approvals set out conditions for the project, including management plans. Management systems will be in place to ensure compliance with all conditions covering construction, operation, decommissioning, and administrative matters.
Enel Green Power Australia (EGPA) will manage the construction works for the project. EGPA has appointed Beon Energy Solutions as the Engineering Procurement and Construction (EPC) contractor for construction.
EGPA is also committed to local sourcing throughout the project’s operational and construction phases, where feasible. It is expected that the project will create significant local employment and supply opportunities during construction.
EGPA will work closely with the main contractors to identify capability and capacity in the local area. The specifics of these roles will be made publicly available in early 2025 by recruitment agency Chandler MacLeod.
For more information visit www.jobsinsolar.com.au or contact Chandler MacLeod at jobsinsolar@chandlermacleod.com Project updates can also be found at www.enelgreenpower.com/our-projects/in-development/quorn-park-hybrid-project